Decom-MISSION Impossible: Shortened Timelines

THE PROJECT MISSION:

What: Decommission of a 60,000 SF warehouse

When: November

How long: Completion prior to the Thanksgiving Holiday

The Details:

  •    removal of all FF&E including power poles for multiple business units, lockers, break room and storage rooms
  •    electrical taken back to the panel
  •    all telephone and IT equipment must be removed and shipped offsite, including cabling and tray removal
  •    all security equipment must be removed and locksets replaced
  •    space must be put back as it was prior to client lease

THE CHALLENGE

Impending lease deadlines and holiday season schedule challenges left DCMS with little wiggle room on the deadline. With multiple business units, IDF and IT decommission as well as cross-country equipment shipments – we had to leverage our project planning skills to ensure our client’s satisfaction.

THE SOLUTION

By taking advantage of unoccupied office spaces, we were able to create a schedule that allowed us to start multiple subcontractors at once. Our daily morning stand up meeting helped to keep everyone informed on schedule and allowed for problem solving prior to experiencing any significant delays. As a team, we were able to effectively communicate both daily & weekly goals, and effectively execute our project plan.

THE RESULT

It was challenging with the amount of work and the size of the space but DCMS completed the building decommission successfully and on time. We relied heavily on teamwork and communication to ensure all deadlines were met and scope was covered.

 

THE FEEDBACK

“As the project lead on the customer side of the Yukon decom, it was great to have a team that communicated and met their commitments throughout the facility decom process. I really appreciated the level of engagement and attention to detail. Matt and Kristen worked to make sure all tasks were completed to satisfaction.” – Client Confidential